Micro-modular data center: sizing and lead time

Short answer: size from the IT load and its growth, then rack count and density, redundancy and backup time. One cabinet of edge equipment fits a Warrior; two to ten cabinets fit a Wizard row; up to 24 or 48 cabinets and 125 kW per module fit a WT-MMDC. Lead time depends on the configuration and the factory schedule, so we confirm it per project: contact us for the current lead time. Because units are integrated and tested in the factory, the work left on site is short.

WincoTek Insights · 20 November 2026 · 5 min read

WincoTek micro-modular formats (values from the micro-modular data center page)

FormatCabinetsUPSCoolingIT loadOn site
Warrior (edge)1 cabinet, 600 / 800 mm wide3 / 6 / 10 kVA, on-lineRack AC 3.5 / 4.2 / 8.1 kWSingle cabinetDeploys in days instead of months; deployment time cut by up to 70%
Wizard (micro)1+1 to 1+9 (2 to 10 cabinets), 42U / 47U10–30 kVA; N, N+1 or 2NRack-mounted or in-row, contained aisleSmall rowOn-site installation in ≤1 day
WT-MMDC (modular)≤24 single channel, ≤48 double channel25–125 kVA, ≥96% efficiencyIn-row 25–60 kW; DX, chilled or cooling water≤125 kW per module (145 kW with integrated PDU)Deployment time reduced by up to 50%

Step 1: IT load, today and later

Start with the power the IT equipment draws, in kW, not the nameplate rating of every server. Add the growth you expect over the life of the room. A micro-modular room grows in steps: a Wizard row by adding racks to its integrated power and cooling cabinet, a WT-MMDC by its cabinet count up to the module limit, and a site by adding modules. Decide which step you are sizing for now and which you will add later.

Step 2: rack count and density

Divide the load into racks. The delivered WT-MMDC projects listed on our site run at 2 to 5 kW per rack, which is typical for enterprise, banking, public-sector and telecom rooms. A room at 4 kW per rack with 20 racks needs about 80 kW of IT capacity, which sits comfortably inside one single-channel WT-MMDC (up to 24 cabinets). The same load at 2 kW per rack takes 40 racks and a double-channel module. If your racks will run far above these densities, for AI or HPC, look at liquid cooling with rack CDUs or a containerized liquid-cooled design instead.

Step 3: redundancy

Redundancy decides how much of the installed capacity you can actually use. With N, one UPS path carries the load; it is the economical baseline for standard edge sites. N+1 adds one spare module so a failed module does not drop the load. 2N provides two complete power paths, from dual feeds through ATS and UPS, with no single point of failure. Every WT-MMDC project on our reference list runs 2N UPS with N+1 in-row cooling. For cooling, N+1 means one standby unit beyond those needed: for roughly 80 kW of IT heat with 40 kW in-row units, that is two duty units plus one standby, before the engineering check of room losses and climate.

Step 4: backup time and battery type

Backup time is how long the UPS carries the load when the utility fails, usually until a generator starts or the systems shut down cleanly. Our delivered micro-modular projects range from 15 minutes on lithium-ion batteries to 2 hours on VRLA batteries. Longer backup means more battery cabinets, more floor space and more weight, so set it from the site's generator arrangement and the cost of downtime rather than a default.

Step 5: cooling medium and site

WT-MMDC in-row units come in 25 to 60 kW capacities and work with DX, chilled water or cooling water systems; choose by what the building already has. Check the site against the module dimensions and the installation method (raised floor, cable entry from top or bottom), the supply voltage (208 to 415 V, 50 or 60 Hz, three-phase) and the fire-suppression approach. Our listed projects use FM-200 with intelligent detection; Warrior cabinets use FM-200 or Novec 1230 units.

Reference projects

Country / sectorConfigurationIT capacityRacksPer rackUPS / coolingBackup
Azerbaijan7× WT-MMDC630 kW1265 kW2N / N+1 in-row15 min Li-ion
Brunei, energy & petrochemical5× WT-MMDC240 kW803 kW2N / N+1 in-row1 h VRLA
China, public safety3× WT-MMDC360 kW1203 kW2N / N+1 in-row2 h VRLA
China, banking & finance8× WT-MMDC224 kW1122 kW2N / N+1 in-row2 h VRLA
China, banking & finance8× WT-MMDC300 kW1502 kW2N / N+1 in-row1 h VRLA

Scope in each project: layout design, power and cooling integration, factory build, factory acceptance test (FAT) and delivery, then installation, commissioning and operation support on site.

What sets the lead time

We do not publish a standard lead time, because it depends on the configuration and on the factory schedule when you order. Contact us with your requirements for the current lead time. What we can describe is the sequence, so you can plan around it:

  • Requirements: load, racks, density, climate and power. A fixed requirement is the fastest way to a firm schedule.
  • Engineering: structural, electrical, HVAC, monitoring and fire drawings for approval.
  • Manufacturing and integration: fabrication, assembly, and connection of all disciplines at our Hangzhou manufacturing base.
  • FAT: the integrated system is tested before release.
  • Shipping and site readiness: transport, plus the work only the site can do, such as utility power, floor preparation and permits. Start this in parallel with manufacturing.
  • Deployment: placement, connection and commissioning. This is where prefabrication saves time: a Wizard row installs in a day or less, and Warrior cabinets deploy in days instead of months.

The main schedule risks are late changes to the requirement and a site that is not ready when the equipment arrives. Freezing the load, redundancy and backup decisions early, and preparing the site while the factory builds, protect the date.

When a micro-modular room is not the right fit

For outdoor sites with no building, or capacity from 100 kW to 10 MW and more, containerized data centers bring the IT hall, power and cooling in factory-built modules. For dense AI clusters, overhead AI PODs and rack CDUs handle liquid cooling well beyond the 2 to 5 kW per rack of a typical micro-modular room.

Send us the IT load, rack count, redundancy level, backup time and site conditions, and we will propose a configuration and confirm the current lead time.

Plan it with us.

Send your requirements and we reply with a matched design, part numbers and a sample or proposal plan.